120MW Laurel Wind Farm
Project Name
Laurel Wind Farm (the “Project”)
Project Owner
Laurel Wind Energy LLC (“LWE”)
Project Developer
RPMA Iowa Wind Development LLC (“RPMA”)
Project Size
121 Megawatts
Project Location
West of town of Laurel; in Jefferson and Logan Townships in Marshall County and Malaka and Mariposa Townships in Jasper County, Iowa
Project Site Area
Approximately 11,000 acres of gently rolling and open farmland where corn and soy beans are the dominant crops
Proposed Generating Equipment
67 Vestas 1.8 MW turbines on 80 meter tubular towers
Proposed Balance of Plant Facilities
Approximately 15 miles of underground electric and data collection cable, 17 miles of gravel service roads, 20 entrances, 3 permanent MET towers, a single 161 kV substation, and a single operations and maintenance building
Amount of Cropland Used for Wind Farm
Approximately 34 acres (less than 1% of total project site area)
Point of Interconnection
New 161 kV substation near Laurel, Iowa; approximately half way between Marshalltown and Jasper substations.
Transmission Provider
Midwest Independent System Operator of Carmel, IN (“MISO”)
Transmission Owner
ITC Midwest LLC of Novi, MI (“ITC”)
Power Purchaser
To Be Announced
Proposed Turbine Supplier
To Be Announced
Proposed Balance of Plant Supplier
To Be Announced
Project Research and Design Engineers
Wind Engineers (Wind Resource, Noise, Shadow) Snyder and Associates (Surveying, Civil, Phase I Environmental, Wetlands) CEG (Electrical) ComSearch (Beam Path) Braun Intertec (Geotech) Zia Engineering (Cultural) Curry and Kerlinger LLC (Phase I Avian)
Early Notice to Proceed
October 1, 2010
Expected Ground Breaking
May 1, 2011
Expected In-Service Date
October 31, 2011
Expected Commercial Operation Date
December 31, 2011