Top of Iowa III Wind Farm

Top of Iowa III Wind Farm

Project Name

Top of Iowa III Wind Farm


Developer

Midwest Renewable Energy Corporation


Owner

Madison Gas and Electric Company


Constructor

Wanzek


Size

29.7 MW


Location

Approx 3 miles west of the Town of Kensett, Worth County, Iowa


Site Area

Approx 1,332  acres of cropland consisting of 10 separate parcels of land


Generating Equipment

18 Vestas 1.65 MW turbines on 260 foot tall tubular towers


Balance of Plant Facilities

6.2  miles of underground electric and data collection cable, 3.8 miles of gravel service roads, 1 permanent MET towers and sharing of the Top of Iowa Wind Farm 161 kV substation


Foundation (each)

Approx 390 cu yards of concrete; 30 tones of reinforced steel


Job Creation

Approx 36,000 person-hours (or 25 people for 6 months) during construction; 1-2 long-term operational


Local County Taxes

Approx $10.3 Million over 25 years


Ground Breaking

April, 2007


Commercial Operation

October, 2007